Masons should be finishing up the brick toward the end of this week while the finishing touches are applied to the windows. Ceiling work was scheduled to begin this week while the cabinets and other casework are ready to be installed. Painting has gotten underway with the primer coat on most of the second floor walls. Site work will also begin late this week on the Winchester Street side of the building, prepping for landscape and walkways. Rooftop equipment is being piped in as control wiring is being connected. Data and security wiring are underway and have made substantial progress.

Photos will be updated on the website sometime this week.