TDS Update

The second floor slab has been poured and the first floor slab will be poured by the end of the week. Saw cuts to the second floor slab will commence the beginning of next week. Framing on the first floor will finish this week as we get closer to being able to sheet rock the office area. Masons will be working on the annex area, building the wall so steel can be erected and the roof can be installed. The roofers have finished covering the main building and continue to finish details to ensure a watertight roof. Electricians and plumbers have been working on their rough-in utilities and will continue to do so as walls start to be framed in the new building within the next couple weeks.