(As of January 4, 2012)

Over the past couple weeks, foundation insulation has been being laid down so the vapor barrier can be installed prior to pouring the concrete floor. The parapet walls have been being built on the roof and roofers are expected to return later this week to begin installation, which should take a little over a week. The annex foundation is coming along and should be finished by the end of the week. Steel erectors have returned to install the lintels that will run along the perimeter of the building. The mockup in the parking lot has been enclosed so the masons can start building a brick wall to serve as a demonstration of quality standards. Plumbers have been installing temporary heat as the winter sets in and a temporary enclosure will be built soon to ensure appropriate temperatures for concrete and mortar curing.