Early next week we will see the first signs of the building “skeleton” arrive on the site. Toward the end of the next week, erection of the steel “skeleton” will begin and is expected to last until early December. The last grade beam and pile cap concrete pour will take place next week and we will be preparing for the structural slab. The site work will continue as they are filling in the foundation with previously excavated dirt and bury the underground utilities. The restroom plumbing in Butterfield is coming along as we start to get a sense of the interior space configuration. This work, and much more, can be seen in the photo section on the TDS website.