The third concrete pour is scheduled for Friday, Oct. 21, marking the rough half way point for the foundation. The grade beams and pile caps should be finished in a couple weeks; then, steel erection will begin. Steel is scheduled to be onsite in two weeks and take two to three weeks to complete. Plumbing work is going on inside Butterfield as the interior demolition is close to being completed. Remember to check in on the TDS website for updated pictures.