Pile driving has finished and so has the major demolition.

For the next three weeks, we can expect concrete trucks being the largest disruption down Blake St.

The electrical primary conduit has been run through the Science Center, so we shouldn’t experience any major parking lot closings in the future. The only major work, besides underslab utilities, will be concrete form work and getting the pile caps and grade beams poured. Check out the TDS website for pictures from the site.