TDS Update

As of September 22, there have been 80 piles driven (69 percent) and that should wrap up late next week. The downstream defender installation will wrap up this week and the Science Center parking lot will reopen. Demolition of Butterfield is about 90 percent complete and should be complete toward the end of next week. Currently there is steel being tied for pile caps and grade beams, giving first indication of the size of the building footprint. Next week, we should see more utilities, steel being tied and possible forms for concrete being erected.