TDS Update

Pile driving has been going on for the last week, and as of Wednesday, 17 piles have been hammered home — only 105 to go! They are vibrating them down as far as they can then using the hammer to make sure it has hit bedrock; currently piles are reaching rock at about 70 feet on average.

The chiller that serves Huntress Hall basement classrooms will be disconnected and relocated toward the end of this week. A/C to the classrooms will be unavailable until it is reconnected, hopefully by the middle of next week.

Butterfield has been cleared of hazardous material. Demolition will begin next week and should wrap up at the end of next week.