With the successful removal of hazardous material from Adams Tech winding down, we can expect more activity at the TDS Center site in the next few weeks. The demolition of Adams Tech is scheduled to begin Monday, August 8 and is expected to last roughly 10 days. Butterfield is currently in the process of being contained so that hazardous material removal can begin.

Some major site demolition began Thursday, July 28. In addition to this site work, remember that Blake Street is through Friday, August 5.

Access to the few parking spots at the Science Center will be available; however, you need to use Madison Street to access them.

Pile driving, one of the loudest parts of the project, will begin Friday, August 19 and is expected to take roughly three weeks.

If you have any questions about construction please call Colin Burdick at 358-2225 or e-mail cburdick@keene.edu.